Client: SAB Miller – Mozambique
Industry: Food and Beverage – Manufacture beer.
Scope of work: To supply and install 3-4mm non slip hard wearing floor.
Floor requirements: Floors needed to be strong, non slip and able to take forklift traffic. Floors also required to be acid and alkali resistant.
Product Spec: Silikal R61 MMA floor
Challenge: Client required fast installation in the shutdown period with other trades needing floor areas to install new bottling and filler machines. LS team worked through the night to get the floors finished so that 30 tons of equipment could be placed on the floors the following day.
Contact: Ian Rathbone – Chief engineer
Feedback: ” Livingstone floors delivered a world class flooring product within a very tight time frame. They not only delivered on time but the end result was the exact floor we required in a very wet environment” Ian Rathbone – Chief Engineer

032PLANT BEING INSTALLED ON FLOOR SAB MILLER 22 TONS BOTTLING 010SAB MILLER - AFTER